| Rework - In most of the manufacturing environment, there would be
some or other form of rework.
This will explains how to handle the rework by creating a new production
order.
By: Vicent
Scenario:
1. When a rework is to be done a new production order is to be created.
2. This production order will not have any material.
3. This will have only one operation.
Assumption
1. A header material HM1 is already setup in the system with all required
master data like BOM, Routing, etc.
Before we go in detail the below T-codes are the one the person is
to be familiar with
Transaction codes:
1. BS02- status profile management
2. CA21- Rate routing
3. C032- Reference rate routing
4. Ca02- Routing change
Configuration:
1. New order type
2. Order type dependent parameters
3. Default operation for the order type / Plant combination.
I. Creation of status profile:
a. Create one status profile Zrework with 2 status in the profile
ex: Initial, Creat.
b. The Status profile should be assigned to object types.
II. Create a separate order type
a. Create a separate order type
b. Set up the order type dependent parameters
c. Now assign the status profile in the header and in the operation
in the created order type
III. Create Rate routing
a. Create a simple rate routing
IV. Create a Trigger Point.
1. Create a trigger point with co31.
2. In the Trigger point assign the status(create ) for the function
- create a new order
3. Double click the assigned status this will pop an additional window
to fill in the group, group counter and order type.
4. Fill in with the rate routing no and also the created order type
V. Routing - Trigger point.
a. Now the trigger point has to be assigned to the routing of the header
material HM1.
b. To assign this double click on the operation and in the Menu - find
the trigger point and assign the trigger point a pop up window requests
you if to copy from std trigger point - confirm yes.
c. After the trigger point is assigned save it .
VI. Test Rework Scenario.
Step 1. Create a production order for the header material HM1-release
and save it.
* Check in the status management if the status ZREWORK.
Step 2. Now confirm the production order with Co11.
* When you confirm make the yield as zero and also delete if any goods
movement was there
Step 3. Now save the confirmation. When you save the confirmation you
will get a trigger point message - confirm the message it will take you
to the next screen where the trigger point with the function to create
the production order would be displayed.
Step 4. Now execute the trigger point. This would generate a production
order.
Now the production order without material is created,
The above explains the rework scenario in higher level, with this input
try out the rework cycle as per the business requirements.
Questions
SAP PP Questionnaire
SAP PP Reference Books:
SAP Production
Planning , Configuration, Interview Questions and Certification, Books
Goto:
SAP MRP - Materials Requirements
Planning Configuration Hints and Tips
Back to:
SAP PP (Production Planning) Configuration
Hints and Tips
Return to :-
SAP ABAP/4 Programming, Basis
Administration, Configuration Hints and Tips
(c) www.gotothings.com All material on this site is
Copyright.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
All product names are trademarks of their respective
companies. The site www.gotothings.com is in no way affiliated
with SAP AG.
Any unauthorised copying or mirroring is prohibited.
|